CompanyOS Implementation Plan. Prepared by Modern Operators for Orange Energizing Solutions (OES). This document contains Modern Operators frameworks and is confidential under Section 10 and Exhibit A of the Agreement.
1. Executive Summary
Where you are today. OES runs every job through yearly Smartsheet sheets, split between local customers and national accounts like 7-Eleven, CVS, Dollar General, and Family Dollar. Because each year and each account lives in its own sheet, nobody can open one record and see a store's full history. Quantities sold versus installed, current status, and money owed by utilities are scattered across columns, comments, and WhatsApp.
What we are building. One shared system for local and national work in Notion. Each site carries its full job history, each project carries its status and money, and each line item records what was sold and what was installed. Inventory, payroll, and customer reports then come from the same numbers.
How we will get there.
- Stage One is the implementation, in three phases: audit, build, and training. Stage Two is the ongoing Operating Partner work after cutover.
- In the build phase, we commit to two workflows end to end: Survey to submitted application, and Install to closeout.
- We also target the other four workflows in the same build. We aim to deliver them within the build phase, and will communicate if any are at risk of slip.
- Your team trains once, on the finished system, not on pieces that are still changing.
How long it takes. Based on what we scoped with your team, we expect the build phase to take about two months once it starts, rather than one. That puts Smartsheet cutover at roughly 120 days from the start of the engagement, or later if inputs from OES run late. This is an estimate, not a deadline. Smartsheet stays live as your system of record until cutover, so nothing is at risk while we build. Your monthly fee does not change.
What we need from you now. Written feedback on this plan and go ahead. If received by Friday 11/27, we’ll plan to start 11/30. Review period ends 12/2/26.
2. What Is Included
This table shows where each item in your Agreement lives in this plan.
Your Agreement includes | Where it shows up |
Foundation CompanyOS, plus access and permissions (Leadership and Staff) | Milestone 1 |
Projects and Tasks system | Milestones 2 and 4 |
Up to two workflows, built and launched with starting records | Survey to submitted application (Workflow 1) and Install to closeout (Workflows 3 and 4), with the data load in Milestone 3 |
Executive Dashboard v1 | Milestone 5: national account reports and the chairman's daily view |
Roles and Ownership layer, and Knowledge Base structure | Milestone 6 |
Two AI agents | Section 8, scoped first, then delivered |
Two training workshops, materials, and administrator handoff | Milestone 7 |
The other four workflows and the owner money dashboard are targets within the same build. Section 9 explains what is committed, what is a target, and what is an add-on.
3. How to Read This Plan
- Workflow: A repeatable sequence of steps that moves one piece of work from start to result, such as a store survey to a submitted utility application. Each step has a named person or team, an action, and a place in CompanyOS where it is recorded.
- Stage One, Stage Two, and the three phases: Stage One is the implementation: Phase 1 audit, Phase 2 build, and Phase 3 training and adoption. Stage Two is the Operating Partner work that continues after cutover.
- Committed, Target, and Add-on: Committed work is in the build and we deliver it. A Target is work we aim to deliver in the same build but do not promise, and we will tell you early if it slips. An Add-on is outside the Agreement and is scoped and quoted separately.
- View, dashboard, and report: A view is a saved way of looking at a database for one role. A dashboard combines several views and numbers on one page. A report is a summary for a specific audience, often shared outside the team.
- SOP and Knowledge Base: An SOP is written step-by-step instructions for one workflow, with a named owner. The Knowledge Base is the searchable library where rules, reference information, and SOPs live.
- Parallel run and cutover: A parallel run is a short period when the team uses the new system while the old one is still available. Cutover is the date the new system becomes the only one in use.
- Automation and AI agent: An automation is a fixed rule that does the same thing every time. An AI agent reads, drafts, or recommends within set limits. A person reviews its output, and it is scoped before it is built.
4. Current State: Key Findings
- No site history. Smartsheet holds standalone sheets per year. There is no site-level ID, and the same store is revisited 5 to 8 times over 10 years.
- Quantities are not tracked as data. About 26 products sit in wide columns. Installed quantities are posted as comments or WhatsApp messages, so inventory counts and installer payroll do not match what was installed.
- Status lags reality. Updates fall behind, and on-hold jobs keep their old status.
- Job detail is not standardized. Missing details such as exact door, electrical specs, fixture type, and ceiling type cause return trips and remakes.
- Field capture is hard. Media uploads fail without Wi-Fi, so technicians fall back to WhatsApp and the office matches files to jobs by hand. About 50 to 70% of field notes are handwritten and retyped.
- Rules live in people's heads. Utility program rules and customer restrictions are settled in comment threads, with no written SOPs or onboarding guide.
- Reporting is manual. National account reports are rebuilt in Excel, the chairman receives a daily Excel export, and QuickBooks is not connected.
- Money is hard to see. The four columns of money and receivables aging are tracked from memory and paper.
- Inventory is disconnected from jobs. About 20 common items have many subtypes, and door gaskets alone come in about 25 profiles.
- Communication is fragmented. WhatsApp is the main channel, so decisions rarely reach the job record.
- Access is all-or-nothing. Field staff must ask the office to edit, and financial data is visible to anyone with sheet access.
- Footprint. About 30 people across Brooklyn, the field, and a team in the Philippines, working in about 10 states, with about 200 active projects.
5. Proposed Architecture
The starting architecture has seven connected databases. It can change as the build and testing progress.
Database | What it holds | What it replaces |
Client Sites | One row per store or customer location, the "customer card" with full history | Re-entering the same store in each year's sheet |
Projects | One row per job, with status, money, and a Log of check-ins and decisions | The yearly local and national sheets |
Line Items | One row per product on a job, with quantity sold, quantity installed, and variance | About 26 wide product columns and quantities in comments |
Products and Inventory | One row per product and subtype, with on hand and reorder point | Manual warehouse tracking |
Trips | One row per field trip, with route link and installers | Trip numbers typed into each row |
People | One row per team member, with role and department | Names typed as free text |
Tasks | One row per task, linked to a project, with parent tasks and subtasks | Requests chased in comments and WhatsApp |
Project IDs: Each project ID becomes the Site Code plus a suffix, such as -1 and -2, so every job traces back to its site.
Status model: We keep the names OES uses today: Unsurveyed, Surveyed, In Progress, Submitted, Approved, Parts Ordered, Parts Ready, Assigned, Installed, Completed. Side statuses are Need Revisit, On Hold with a reason in the Log, Nothing Needed, and Cancelled. "Submitted" is the only new status. It separates the third and fourth columns of money and needs your confirmation.
Role views: Advisor pipeline, Utility Programs queue, Warehouse, Installer Manager, Technician, Office Closeout, and Payroll, plus a store history view on each Client Site and a report view for each national account.
Money and reporting layer: The fields are built regardless. They group the four columns of money from project status: installed and waiting on the utility, approved and waiting to install, submitted and waiting on approval, and sold but not submitted. Receivables aging is calculated from install date for projects with no payment date.
Roles and knowledge: The Roles and Ownership layer maps who owns what to each role in People. The Knowledge Base is seeded with utility program rules, customer restrictions, and SOPs for the two workflows we build.
How OES's other tools fit.
System | Handling during the build |
Smartsheet | Stays live as the system of record during the build. One load of 2026 records for the two built workflows, then read-only at cutover once OES signs off. History beyond 2026 is an add-on. |
SharePoint and OneDrive | Stay. Folder links are stored on each Client Site and Project. |
WhatsApp | Stays for conversation. Decisions and quantities are recorded in the project Log and Line Items. |
Outlook and email | Stay, outside the system. |
Google Form (survey intake) | Stays while we explore one or two Notion forms, one for the project and one for its line items. This may need some manual effort. |
Work orders (Google form and paper) | Stay outside CompanyOS. The signed copy is saved in the project's SharePoint folder. |
Utility portals and application tools | Stay, owned by each utility. Results are entered on the Project. |
Excel reports | Replaced by national account and chairman report views. |
QuickBooks | Out of scope. Payment dates are entered manually until a later integration. |
Route software and Google Maps | Stay. The route link is stored on each Trip. |
Key decisions already made. Start Notion fresh. One shared architecture for local and national accounts. Large files and videos stay on SharePoint. Current status names are kept. Line Items are a separate database, not product columns. Utility program rules live in the Knowledge Base.
6. Workflow Designs
We design all six workflows now and build them in Phase 2, over about two months. Workflow 1, and Workflows 3 and 4 together, are committed. Workflows 2, 5, and 6 are targets within the same build, and any that do not fit move to the Operating Partner work after cutover, in the order you set at the monthly priorities session.
Workflow 1: Survey to submitted application (committed)
Step | Who | Action | In CompanyOS |
1 | Energy advisor | Surveys the store and submits the survey with photos and videos | New Project (Surveyed) linked to a Client Site, with Line Items |
2 | Office | Checks required documents and adds the Media Folder link | Closeout checklist and Media Folder, with a Task for anything missing |
3 | Utility programs team | Pulls utility customer details and builds the application | Utility Customer ID on the site, Status In Progress |
4 | Utility programs team | Enters estimated incentive and savings | Est. Incentive and Savings fields on the Project |
5 | Sassi | Signs the application | Signing queue view, Status Submitted |
Workflow 2: Approval to assignment (target, built in the same Phase 2 build)
Step | Who | Action | In CompanyOS |
1 | Utility programs team | Records utility approval | Status Approved, purchasing notified |
2 | Purchasing | Checks stock, orders or manufactures what is missing | Line Item Parts Status and PO number |
3 | Purchasing | Marks parts ready | Status Parts Ordered, then Parts Ready |
4 | Installer manager | Assigns installers and adds the job to a trip | Installers and Trip fields, Status Assigned |
5 | Operations | Builds the route and records booking details | Trip route link and status |
Workflow 3: Install in the field (committed, together with Workflow 4)
Step | Who | Action | In CompanyOS |
1 | Technician | Opens today's stores and sees items, quantities, and media requirements | Technician view and Line Items |
2 | Technician | Checks in | Project Log entry |
3 | Technician | Installs and records actual quantities | Qty Installed, with Variance shown |
4 | Technician | Uploads pre and post media | Media Folder on SharePoint |
5 | Technician | Gets the signed work order and checks out | Signed copy in Media Folder, Status Installed |
6 | Technician | Flags a revisit if work could not be finished | Status Need Revisit, Task for parts |
Workflow 4: Closeout, utility payment, and payroll (committed, with Workflow 3)
Step | Who | Action | In CompanyOS |
1 | Office | Completes post-install paperwork and submits to the utility | Closeout checklist |
2 | Office | Invoices the customer's share and records payment | Customer Cost and Closeout fields |
3 | Office | Records the utility payment | Actual Incentive and paid date, Status Completed |
4 | Office | Runs installer payroll | Payroll view of Qty Installed by installer and date |
5 | Purchasing | Reconciles inventory | Line Item Variance and On Hand count |
Workflow 5: National account reporting (report views are part of Executive Dashboard v1 and committed; store-list loading is a target in the same build)
Step | Who | Action | In CompanyOS |
1 | Operations | Loads the customer's store list | Client Sites and Projects with Status Unsurveyed |
2 | Field and office team | Run Workflows 1 to 4 for each store | Same Projects, Line Items, and Trips |
3 | Operations | Shares the weekly or biweekly report | National account report view, exported if a file is needed |
Workflow 6: Weekly money review (target, built in the same Phase 2 build with the owner dashboard)
Step | Who | Action | In CompanyOS |
1 | Leadership and finance | Review the four columns of money and receivables aging | Owner dashboard if built, otherwise Projects table views |
2 | Leadership | Follows up on items waiting on utility payment past 90 days | Aging view and Tasks |
7. Milestones and Timeline
Milestones run from foundation to features: workspace and access, then databases, then data, then views and dashboards, then roles and the knowledge base, then training and cutover. All dates are targets, not fixed. Under your Agreement, phases follow readiness and day counts are estimates. If answers, access, or testing from OES run late, our dates move by the same number of days.
Key dates. Plan feedback by Friday 11/27. Full build starts Monday 11/30 with your written go-ahead. CFO call 12/2. Roles and ownership are a target for the middle of the build. Smartsheet cutover is set once testing is finished and OES signs off.
When build starts. After we deliver this plan, you have five business days to decide whether to continue under the Agreement. The full build starts Monday 11/30 if you tell us in writing to go ahead. If we do not hear from you, it starts when the five-day window closes, about 12/2.
How long the build takes. We expect the Phase 2 build to take about two months once it starts, rather than one, which puts Smartsheet cutover at roughly 120 days from the start of the engagement, or later if inputs from OES run late. This is an estimate, not a deadline. The monthly fee in your Agreement does not change.
Training comes last. Training and adoption begin only when the build is substantially complete, as described in Section 4.5 of your Agreement. Your team is trained once, on the finished system.
Milestone | What it delivers | Done when | Owners |
1. Workspace foundation and access | Workspace structure, People and Tasks databases, department-based access rules designed now and applied as staff are added, Modern Operators access to Smartsheet and SharePoint | Leadership can access the workspace and Modern Operators can export every 2026 sheet | OES: Sassi. MO: Selina |
2. Core databases | Client Sites, Projects, Line Items, Products and Inventory, and Trips, with the status model and Log template | A sample site with two projects, line items, and a trip can be entered end to end | MO: Selina. OES: purchasing, operations review |
3. 2026 data load | One load of 2026 local and national records for the two built workflows, with a short list of rows that need an OES decision | Counts reconcile with Smartsheet exports, apart from an exceptions list OES has approved | MO: import map and load. OES: fix exceptions and approve the list |
4. Role views and intake | Advisor, Utility Programs, Warehouse, Installer Manager, Technician, Office Closeout, and Payroll views, survey intake, notification to purchasing at Approved | Each role lead runs one real project through their view without using Smartsheet | MO: Selina. OES: each role lead |
5. Executive Dashboard v1 | National account report views and the chairman's daily view. The owner money dashboard is an expansion, not committed | One national account report is sent from Notion and the chairman's daily view is live | MO: Selina. OES: leadership, operations, finance |
6. Roles, knowledge base, and SOPs | Roles and Ownership layer and Knowledge Base structure loaded with the rules OES provides. SOPs for the two built workflows come first, more are a target | Structure is built and holds the content OES has provided | OES: approval and rules content, role leads for SOPs. MO: structure and drafting |
7. Training, parallel run, and cutover | Role-based training on the finished build, a short parallel run, administrator handoff, and Smartsheet set to read-only for the work built. Smartsheet stays live until cutover. | Training is delivered, role leads finish parallel-run testing, and Sassi signs off on cutover | OES: Sassi and role leads. MO: Selina |
Milestone 7 depends on substantial completion of Milestones 1 to 4. Milestones 5 and 6 are not required for cutover.
8. AI Agents
Your Agreement includes two AI agents. We scope each one before we build it. Scoping covers the data the agent needs, where it runs, who reviews its output, and how it fits the timeline. After scoping, we confirm which two to build and when, based on how ready the system is. The options below are what we will scope from.
Requested by OES leadership
- Voice-to-work-order. Turns a technician's or advisor's voice note into a project with line items.
- Voice-note survey. Captures the advisor's survey by voice instead of typing. Optional.
Options we suggest
- Program rules checker. Flags line items that may break a utility or customer rule, for human review.
- Missing documents check. Lists projects missing photos, bills, or paperwork before submission or closeout.
- Handwritten note reader. Reads a photo of a handwritten field note and drafts line items for office review.
- National report summary. Writes the weekly summary paragraph for each national account report.
Before any voice or document-reading agent is built, we scope recording-consent notices by state, data retention, and a human-review step.
9. Scope and Boundaries
This section explains what the build includes, what OES owns along the way, and what sits outside it. If anything here differs from your Agreement, the Agreement controls.
Committed in the Phase 2 build (Expected to last 2 months)
- Workspace foundation, the Roles and Ownership layer, and the Knowledge Base structure.
- The initial databases listed in Section 5. The structure may change as discovery, build, and testing progress.
- Two workflows, built and launched with initial records: Survey to submitted application, and Install to closeout.
- Role views as needed for advisors, utility programs, warehouse, installer manager, technicians, office closeout, and payroll.
- A one-time load of 2026 Smartsheet data for those two workflows. We build the import map and run the load. OES staff fix exceptions and approve the reconciliation list.
- Survey intake and the notification to purchasing at Approved.
- Executive Dashboard v1: national account report views and the chairman's daily view.
Targets within the same Phase 2 build (we aim to deliver, not committed)
- Workflow 2, the store-list loading in Workflow 5, and Workflow 6.
- The owner money dashboard.
- Anything that does not fit in the build moves to the Operating Partner work after cutover, in the order you set.
- An SOP for each workflow and an onboarding checklist, written with the role leads who use them. How many we finish depends on what OES already has and how much time role leads have.
Phase 3
- Delivery of two AI agents, scoped first.
- Two live training workshops
- Aadministrator handoff
- Smartsheet cutover for the work built.
Add-ons (scoped and quoted separately)
- Historical data import beyond 300 records from 2026 and data prior to 2025, scoped by hours after we review the exports.
What OES owns
- Decisions. We ask Sassi to answer blocking and pending questions within 36 hours. Your Agreement asks for answers within 48 business hours where reasonably possible.
- Timing. If answers, access, or testing run late, our target dates move by the same number of days, and monthly fees continue as described in the Agreement.
- System owner. A named team member is the first contact for questions and keeps the data clean.
- Content. Purchasing, operations, and utility programs provide the product list, program rules, and media requirements.
- Accuracy. OES supplies and owns program rules, quantities, incentive figures, and pay figures, and checks them before any utility submission or payroll run. We build structure only. The Payroll view is advisory until OES reconciles a parallel payroll run.
- Data. After cutover, OES staff enter and update records. Modern Operators does not do data entry or maintain records.
- Costs. OES pays for all Notion seats, add-ons, and third-party tools, as set out in Sections 7 and 10.5 of the Agreement.
- Testing and adoption. Each role lead runs real projects through their view and finishes parallel-run testing. Leads move their teams off Smartsheet and WhatsApp updates onto the Log and Line Items.
Out of scope
- All Roadmap items, connecting QuickBooks or the bank, replacing utility application tools, moving media files out of SharePoint, and building a client portal.
10. Risks and Assumptions
Risk or assumption | Likelihood | Impact | How we handle it |
Field staff keep using WhatsApp instead of the Technician view | Medium | High | One simple Technician view, short training, and role leads checking the Log weekly |
Media uploads still fail without Wi-Fi | High | Medium | Folder link per job, late uploads recorded in the Log, offline upload on the Roadmap |
Imported data is messy | High | Medium | Clean during import using Site Codes, a fixed state list, and People links. OES fixes the exceptions list |
Double entry during the parallel run | High | Medium | Keep the parallel run short, set a clear cutover date once testing is done |
Finance answers arrive late | Medium | Medium | Build Executive Dashboard v1 from project data first, add finance figures after the CFO call |
OES answers, access, or testing run late | Medium | High | Target dates move day for day, and we flag delays early |
Utility programs open or close without notice | Medium | Medium | Program rules kept in the Knowledge Base with an owner and review date |
Assumption: the roughly 200 active projects include national accounts | n/a | n/a | Confirmed against the import counts in Milestone 3 |
11. Decisions and Next Steps
Needed from Sassi to start
Written feedback or a thumbs up on this plan and move forward by Friday 11/27 (Review deadline 12/2/26).
Smartsheet user for Modern Operators, already provided.
Requirements to run the build
- Access. Notion Workspace Owner access for Modern Operators, a named OES co-owner, a Smartsheet user, access to the SharePoint client and job folders, and Notion accounts for every team member who uses the system, added later in the build.
- Team time (requested). A named OES system owner for 1-3 hours a week during the build, each role lead for about 1 hour a week for reviews and testing, and Sassi for about 1 hour a week for review & decisions.
- Inputs from OES. Smartsheet exports for 2026, the product list, the programs and media requirements sheet, sample national account reports, current work order forms, and the team list.
What happens next
- You review this plan and send feedback by Friday 11/27.
- We update the plan for any changes and confirm the two workflows in writing.
- With your written go-ahead, the full build starts Monday 11/30.
- We hold a weekly check-in during the build and flag any delay early.
12. Roadmap
Roadmap items are future ideas and are not part of the Stage One build. They become add-ons or Operating Partner work once scoped. You can find them on your shared page, in the Roadmap Items (Future Wishlist) section, so nothing is lost.